- | ==Monday== | + | ==Monday 6/14== |
* Discussed procuring items & lab space. | * Discussed procuring items & lab space. | ||
* Prepared for SURF start. | * Prepared for SURF start. | ||
- | ==Tuesday== | + | ==Tuesday 6/15== |
- | * Created GANTT Chart ( | + | * Created GANTT Chart (right) detailing our work plan for the summer. |
[[Image:IGEM_Gantt_Chart.gif|thumb|GANTT Chart diagramming our planned progress throughout the summer.]] | [[Image:IGEM_Gantt_Chart.gif|thumb|GANTT Chart diagramming our planned progress throughout the summer.]] | ||
Line 20: | Line 20: | ||
* Cleaned out lab space | * Cleaned out lab space | ||
* Prepared LB-amp media & plates | * Prepared LB-amp media & plates | ||
- | ==Wednesday== | + | ==Wednesday 6/16== |
* Procured remaining antibiotics & sample of XL1 Blue cells | * Procured remaining antibiotics & sample of XL1 Blue cells | ||
* Prepare orders for Sigma, NEB, and others | * Prepare orders for Sigma, NEB, and others | ||
Line 28: | Line 28: | ||
** Addl Lysis bricks | ** Addl Lysis bricks | ||
** Agarase bricks | ** Agarase bricks | ||
- | ==Thursday== | + | ==Thursday 6/17== |
*Made stock solutions for transformation and subsequent culturing | *Made stock solutions for transformation and subsequent culturing | ||
*Transformed XL-1 Blue E. Coli with selected BioBricks | *Transformed XL-1 Blue E. Coli with selected BioBricks | ||
Line 34: | Line 34: | ||
- | ==Friday== | + | ==Friday 6/18== |
*Checked transformation | *Checked transformation | ||
*Minipreped transformed bacteria | *Minipreped transformed bacteria |
Revision as of 23:19, 21 June 2010
People
|
Back to Notebook
Monday 6/14
Tuesday 6/15
Wednesday 6/16
Thursday 6/17
Friday 6/18
|