Week 1
From 2010.igem.org
(Difference between revisions)
Line 24: | Line 24: | ||
* Prepared list of biobricks to order | * Prepared list of biobricks to order | ||
** Addl Lysis bricks | ** Addl Lysis bricks | ||
- | ** | + | ** Agarase bricks |
Revision as of 23:30, 16 June 2010
Contents |
Team
Monday
- Discussed procuring items & lab space.
- Prepared for SURF start.
Tuesday
- Created GANTT Chart (below) detailing our work plan for the summer.
- Detailed possible side projects, open to any member as time permits:
- Agarase
- pH/Environmental Response
- Phototaxis
- Colored plastic
- Activa (transglutaminase)
- Procured supplies from stock room
- Cleaned out lab space
- Prepared LB-amp media & plates
Wednesday
- Procured remaining antibiotics & sample of XL1 Blue cells
- Prepare orders for Sigma, NEB, and others
- Sigma: Crosslinking compounds, substrates (linseed oil & soybean oil)
- NEB: Biobrick assembly kit, Ladders, polymerase
- Prepared list of biobricks to order
- Addl Lysis bricks
- Agarase bricks