Week 1

From 2010.igem.org

(Difference between revisions)
(New page: ===Team=== ==Monday== * Discussed procuring items & lab space. * Prepared for SURF start. ==Tuesday== * Created GANTT Chart (below) detailing our work plan for the summer. [File: IGEM_Gan...)
Line 6: Line 6:
* Created GANTT Chart (below) detailing our work plan for the summer.
* Created GANTT Chart (below) detailing our work plan for the summer.
-
[File: IGEM_Gantt_Chart.gif|thumb|alt="GANTT Chart diagramming our planned progress throughout the summer."]
+
[[Image:IGEM_Gantt_Chart.gif|thumb|GANTT Chart diagramming our planned progress throughout the summer.]]
* Detailed possible side projects, open to any member as time permits:
* Detailed possible side projects, open to any member as time permits:

Revision as of 23:01, 16 June 2010

Contents

Team

Monday

  • Discussed procuring items & lab space.
  • Prepared for SURF start.

Tuesday

  • Created GANTT Chart (below) detailing our work plan for the summer.
GANTT Chart diagramming our planned progress throughout the summer.
  • Detailed possible side projects, open to any member as time permits:
    • Agarase
    • pH/Environmental Response
    • Phototaxis
    • Colored plastic
    • Activa (transglutaminase)
  • Procured supplies from stock room
  • Cleaned out lab space
  • Prepared LB-amp media & plates

Wednesday

  • Procured remaining antibiotics & sample of XL1 Blue cells
  • Prepare orders for Sigma, NEB, and others
    • Sigma: Crosslinking compounds, substrates (linseed oil & soybean oil)
    • NEB: Biobrick assembly kit, Ladders, polymerase
  • Prepared list of biobricks to order
    • Addl Lysis bricks
Retrieved from "http://2010.igem.org/Week_1"